Virginia House Bill 466: State Corporation Commission; time frame for completion of certain proceedings.

Virginia · 2026 Regular Session

What it does

State Corporation Commission; time frame for completion of certain proceedings. Requires the State Corporation Commission to complete proceedings involving an application for a certificate, permit, or approval required for the construction or operation by a public utility of certain transmission lines within nine months following such application, as required by current law for small renewable energy projects. The bill permits the Commission to enlarge such nine-month period for up to 120 days for applications regarding certain transmission lines. This bill is identical to SB 310.

Latest action

Acts of Assembly Chapter text (CHAP0148) (2026-04-06)

See how HB 466 affects you on CapitolKey

Browse more bills · CapitolKey home